| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.06 UNKNOWN ARCHAEOLOGICAL REMAINS |
| D.06. | The entire Mission Bay Project Area has ...
 | 9/21/2000
 | 10/17/2000
 |
 | 12/4/2000
 | Pending City Action
 |
| E.04 THIRD STREET/THE COMMON |
| E.04a. | Install new traffic signals....
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.05 THIRD STREET/SOUTH STREET |
| E.05a. | Install a new traffic signal....
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.47 TRANSPORTATION SYSTEM MANAGEMENT (TSM) PLAN |
| E.47. | Prepare a TSM Plan, which could include ...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 A conceptual TSM and strategic plan was prepared and subsequently approved on May 4, 1999.
 |
| E.47a. | Shuttle Bus System
Operate shuttle bu...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47b. | Transit Pass Sales
Sell transit passe...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47c. | Employee Transportation Subsidies
Pro...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47e. | Secure Bicycle Parking
Provide secure...
 | 9/15/2000
 | 10/23/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47f. | Appropriate Street Lighting.
Ensure t...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47g. | Transit, Pedestrian and Bicycle Route In...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47h. | Parking Management Guidelines
Establi...
 | 9/15/2000
 | 10/20/2000
 |
 | 5/4/1999
 | 5/4/1999 Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| J.01 RISK MANAGEMENT PLAN(S) |
| J.01. | Prior to any site development activities...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999: Phase 1 Approved
 | 5/25/1999 Completed
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| E.04 THIRD STREET/THE COMMON |
| E.04a. | Install new traffic signals....
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.05 THIRD STREET/SOUTH STREET |
| E.05a. | Install a new traffic signal....
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.21 THIRD STREET |
| E.21c. | In cooperation with the Public Transport...
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.28 MUNI LINE 30-STOCKTON OR 45-UNION/STOCKTON |
| E.28. | Extend about half of the 30-Stockton or ...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.28a. | Construct Mission Bay Street, the Sevent...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.28b. | If item E.28a is not feasible sufficient...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.28c. | If item E.28a is not feasible sufficient...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| E.28d. | Use a combination of items E.28b and E.2...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| F.02 CONSTRUCTION PM |
| F.02e. | Sweep streets daily (preferably with wat...
 | 9/18/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| H.07 CORROSIVITY |
| H.07. | Test soils for sulfate and chloride cont...
 | 9/12/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP) |
| K.01. | Develop and implement a comprehensive St...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
 |
| K.01a. | Minimize dust during demolition, grading...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01b. | Minimize wind and water erosion on tempo...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01c. | Minimize the area and length of time dur...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01d. | Prevent the release of construction poll...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01e. | As needed, install filter fences around ...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01f. | Follow design and construction standards...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| K.01g. | Install and maintain sediment and oil an...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01h. | Clean wheels and cover loads of trucks c...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01I. | Implement a hazardous material spill pre...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.03 SEWER IMPROVEMENT DESIGN |
| K.03. | Design and construct sewer improvements ...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.04 ALTERNATIVE TECHNOLOGIES TO IMPROVE STORMWATER DISCHARGE QUALITY |
| K.04. | Implement alternative technologies or us...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.05 CENTRAL/BAY BASIN STORMWATER MANAGEMENT PROGRAM |
| K.05. | Develop and implement a Stormwater Manag...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | The Stormwater Management Plan was completed and deemed acceptable in October 2001 by the Department of Public Works. Individual requirements may apply to all sites.
 |
| K.06 STRUCTURE PLACEMENT AND DESIGN TO MINIMIZE DANGERS OF FLOODING |
| K.06. | Structures in the Project Area should be...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06a. | Setback from the water’s edge...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06b. | Install seawalls, dikes, and/or berms du...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06c. | Provide for dewatering basements...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06d. | Construct streets and sidewalks above ex...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06e. | Use topsoil to raise the level of public...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| K.06f. | Use half-basements and partially depress...
 | 9/18/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| M.03 EXTEND AUXILIARY WATER SUPPLY SYSTEM |
| M.03. | Extend the Auxiliary Water Supply System...
 | 9/20/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Construction and Inspection
 |
| M.05 STORMWATER RUNOFF CONTROL AND DRAINAGE |
| M.05. | Drain stormwater runoff (up to a 5-year ...
 | 10/16/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Permit(s)
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.01 LIGHTING AND GLARE |
| D.01. | Design parking structure lighting to min...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Design Submission
 |
| D.07 PEDESTRIAN-LEVEL WINDS |
| D.07. | Require a qualified wind consultant to r...
 | 9/18/2000
 | 10/20/2000
 |
 |
 | Pending Design Submission
 |
| G.01 NOISE REDUCTION IN PILE DRIVING |
| G.01. | Use noise-reducing pile driving techniqu...
 |
 |
 |
 |
 | Pending Building Site Permit(s)
 |
| K.02 CHANGES IN SANITARY SEWAGE QUALITY |
| K.02. | In addition to developing and implementi...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending City Action
 |
| M.02 WATER CONSERVATION IN BUILDINGS AND IRRIGATION |
| M.02. | Include methods of water conservation in...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| M.02a. | Install water conserving dishwashers and...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| M.02b. | Install water conserving dishwashers and...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| M.02c. | Incorporate water efficient laboratory t...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| M.02d. | Provide information to residences and bu...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| M.02f. | Design landscaping using drought resiste...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Construction and Inspection
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP) |
| K.01. | Develop and implement a comprehensive St...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
 |
| K.01a. | Minimize dust during demolition, grading...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01b. | Minimize wind and water erosion on tempo...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01c. | Minimize the area and length of time dur...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01d. | Prevent the release of construction poll...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01e. | As needed, install filter fences around ...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01f. | Follow design and construction standards...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| K.01g. | Install and maintain sediment and oil an...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01h. | Clean wheels and cover loads of trucks c...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| K.01I. | Implement a hazardous material spill pre...
 | 9/21/2000
 | 9/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Pending Submission of Site Specific SWPPP
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.06 UNKNOWN ARCHAEOLOGICAL REMAINS |
| D.06. | The entire Mission Bay Project Area has ...
 | 9/21/2000
 | 10/17/2000
 |
 | 10/17/2000
 | Pending City Action
 |
| F.02 CONSTRUCTION PM |
| F.02. | As conditions of construction contracts,...
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02a. | Water all active construction areas at l...
 | 10/16/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02b. | Use tarpaulins or other effective covers...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02c. | Pave, apply water three times daily, or ...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02d. | Sweep all paved access routes, parking a...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02f. | Hydroseed or apply (non-toxic) soil stab...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02g. | Enclose, cover, water twice daily or app...
 | 9/21/2000
 |
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02h. | Limit traffic speeds on unpaved roads to...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02I. | Install sandbags or other erosion contro...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02j. | Replant vegetation in disturbed areas as...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02k. | Install wheel washers for all exiting tr...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02l. | Install wind breaks, or plant trees / ve...
 |
 |
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02m. | Suspend excavation and grading on large ...
 |
 |
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| F.02n. | Limit the area subject to excavation, gr...
 | 9/21/2000
 | 10/20/2000
 |
 | 12/4/2000: Phase 1 Approved
 | Conditioned on Subdivision Map and/or Improvement Plans
 |
| I.01 BIOHAZARDOUS MATERIALS HANDLING GUIDELINES |
| I.01. | Require businesses that handle biohazard...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Submission of Evidence of Certification
 |
| I.02 USE OF HEPA FILTERS |
| I.02. | Require businesses handling biohazardous...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Submission of Evidence of Certification
 |
| I.03 HANDLING OF BIOHAZARDOUS MATERIALS |
| I.03. | Require businesses handling biohazardous...
 | 9/21/2000
 | 10/20/2000
 |
 |
 | Pending Submission of Evidence of Certification
 |
| J.01 RISK MANAGEMENT PLAN(S) |
| J.01a. | RMP Enforcement
Provide an enforcement ...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | Timing of implementation triggered by City Fire Department review of cumulative development.
 |
| J.01b. | Pre-Development
Include, at a minimum...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01c. | For areas where ITLs are exceeded, ident...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01d. | Development
Include in the RMP, health ...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01e. | Identify site access controls to be impl...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01f. | Identify protocols for managing soil dur...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01g. | Identify protocols for managing groundwa...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01h. | Include SWPPP requirements and BMPs as d...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01I. | Include a requirement that construction ...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01j. | Develop and describe procedures for impl...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |
| J.01k. | Establish procedures, as necessary, so t...
 | 10/6/2000
 | 10/20/2000
 |
 | 5/25/1999
 | See Implementation Notes for J.01a.
 |