Mission Bay
San Francisco, CA

Block Summary Report

Block: 26a
Click here to view a Printable Summary Report.
If you do not have Adobe Acrobat Reader, please click on the link to download the free plug-in.

Applicable Phase: Major Phase
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.06 UNKNOWN ARCHAEOLOGICAL REMAINS
D.06.The entire Mission Bay Project Area has ...
9/21/2000
10/17/2000

10/17/2000
Pending City Action
E.04 THIRD STREET/THE COMMON
E.04a.Install new traffic signals....
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.05 THIRD STREET/SOUTH STREET
E.05a.Install a new traffic signal....
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.47 TRANSPORTATION SYSTEM MANAGEMENT (TSM) PLAN
E.47.Prepare a TSM Plan, which could include ...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
A conceptual TSM and strategic plan was prepared and subsequently approved on May 4, 1999.
E.47a.Shuttle Bus System Operate shuttle bu...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47b.Transit Pass Sales Sell transit passe...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47c.Employee Transportation Subsidies Pro...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47e.Secure Bicycle Parking Provide secure...
9/15/2000
10/23/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47f.Appropriate Street Lighting. Ensure t...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47g.Transit, Pedestrian and Bicycle Route In...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47h.Parking Management Guidelines Establi...
9/15/2000
10/20/2000

5/4/1999

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
J.01 RISK MANAGEMENT PLAN(S)
J.01.Prior to any site development activities...
10/6/2000
10/20/2000

5/25/1999

5/25/1999
Completed


Applicable Phase: Tentative Map
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
E.04 THIRD STREET/THE COMMON
E.04a.Install new traffic signals....
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.05 THIRD STREET/SOUTH STREET
E.05a.Install a new traffic signal....
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.21 THIRD STREET
E.21c.In cooperation with the Public Transport...
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.28 MUNI LINE 30-STOCKTON OR 45-UNION/STOCKTON
E.28.Extend about half of the 30-Stockton or ...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.28a.Construct Mission Bay Street, the Sevent...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.28b.If item E.28a is not feasible sufficient...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.28c.If item E.28a is not feasible sufficient...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
E.28d.Use a combination of items E.28b and E.2...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
F.02 CONSTRUCTION PM
F.02e.Sweep streets daily (preferably with wat...
9/18/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
H.07 CORROSIVITY
H.07.Test soils for sulfate and chloride cont...
9/12/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP)
K.01.Develop and implement a comprehensive St...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
K.01a.Minimize dust during demolition, grading...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01b.Minimize wind and water erosion on tempo...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01c.Minimize the area and length of time dur...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01d.Prevent the release of construction poll...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01e.As needed, install filter fences around ...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01f.Follow design and construction standards...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
K.01g.Install and maintain sediment and oil an...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01h.Clean wheels and cover loads of trucks c...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01I.Implement a hazardous material spill pre...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.03 SEWER IMPROVEMENT DESIGN
K.03.Design and construct sewer improvements ...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.04 ALTERNATIVE TECHNOLOGIES TO IMPROVE STORMWATER DISCHARGE QUALITY
K.04.Implement alternative technologies or us...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.05 CENTRAL/BAY BASIN STORMWATER MANAGEMENT PROGRAM
K.05.Develop and implement a Stormwater Manag...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
The Stormwater Management Plan was completed and deemed acceptable in October 2001 by the Department of Public Works. Individual requirements may apply to all sites.
K.06 STRUCTURE PLACEMENT AND DESIGN TO MINIMIZE DANGERS OF FLOODING
K.06.Structures in the Project Area should be...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06a.Setback from the water’s edge...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06b.Install seawalls, dikes, and/or berms du...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06c.Provide for dewatering basements...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06d.Construct streets and sidewalks above ex...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06e.Use topsoil to raise the level of public...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
K.06f.Use half-basements and partially depress...
9/18/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
M.03 EXTEND AUXILIARY WATER SUPPLY SYSTEM
M.03.Extend the Auxiliary Water Supply System...
9/20/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Pending Construction and Inspection
M.05 STORMWATER RUNOFF CONTROL AND DRAINAGE
M.05.Drain stormwater runoff (up to a 5-year ...
10/16/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Permit(s)


Applicable Phase: Project Level Review
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.01 LIGHTING AND GLARE
D.01.Design parking structure lighting to min...
9/21/2000
10/20/2000


Pending Design Submission
D.07 PEDESTRIAN-LEVEL WINDS
D.07.Require a qualified wind consultant to r...
9/18/2000
10/20/2000


Pending Design Submission
G.01 NOISE REDUCTION IN PILE DRIVING
G.01.Use noise-reducing pile driving techniqu...




Pending Building Site Permit(s)
K.02 CHANGES IN SANITARY SEWAGE QUALITY
K.02.In addition to developing and implementi...
9/21/2000
10/20/2000


Pending City Action
M.02 WATER CONSERVATION IN BUILDINGS AND IRRIGATION
M.02.Include methods of water conservation in...
9/21/2000
10/20/2000


Pending Construction and Inspection
M.02a.Install water conserving dishwashers and...
9/21/2000
10/20/2000

Phase 1 Approved
Pending Construction and Inspection
M.02b.Install water conserving dishwashers and...
9/21/2000
10/20/2000

Phase 1 Approved
Pending Construction and Inspection
M.02c.Incorporate water efficient laboratory t...
9/21/2000
10/20/2000

Phase 1 Approved
Pending Construction and Inspection
M.02d.Provide information to residences and bu...
9/21/2000
10/20/2000

Phase 1 Approved
Pending Construction and Inspection
M.02f.Design landscaping using drought resiste...
9/21/2000
10/20/2000

Phase 1 Approved
Pending Construction and Inspection


Applicable Phase: Improvement Plan - Plan Check
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP)
K.01.Develop and implement a comprehensive St...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
K.01a.Minimize dust during demolition, grading...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01b.Minimize wind and water erosion on tempo...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01c.Minimize the area and length of time dur...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01d.Prevent the release of construction poll...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01e.As needed, install filter fences around ...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01f.Follow design and construction standards...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
K.01g.Install and maintain sediment and oil an...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01h.Clean wheels and cover loads of trucks c...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01I.Implement a hazardous material spill pre...
9/21/2000
9/20/2000

12/4/2000:
Phase 1 Approved
Pending Submission of Site Specific SWPPP


Applicable Phase: Building Site Permit
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.06 UNKNOWN ARCHAEOLOGICAL REMAINS
D.06.The entire Mission Bay Project Area has ...
9/21/2000
10/17/2000

10/17/2000
Pending City Action
F.02 CONSTRUCTION PM
F.02.As conditions of construction contracts,...
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02a.Water all active construction areas at l...
10/16/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02b.Use tarpaulins or other effective covers...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02c.Pave, apply water three times daily, or ...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02d.Sweep all paved access routes, parking a...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02f.Hydroseed or apply (non-toxic) soil stab...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02g.Enclose, cover, water twice daily or app...



12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02h.Limit traffic speeds on unpaved roads to...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02I.Install sandbags or other erosion contro...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02j.Replant vegetation in disturbed areas as...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02k.Install wheel washers for all exiting tr...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02l.Install wind breaks, or plant trees / ve...



12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02m.Suspend excavation and grading on large ...



12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02n.Limit the area subject to excavation, gr...
9/21/2000
10/20/2000

12/4/2000:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
I.01 BIOHAZARDOUS MATERIALS HANDLING GUIDELINES
I.01.Require businesses that handle biohazard...
9/21/2000
10/20/2000


Pending Submission of Evidence of Certification
I.02 USE OF HEPA FILTERS
I.02.Require businesses handling biohazardous...
9/21/2000
10/20/2000


Pending Submission of Evidence of Certification
I.03 HANDLING OF BIOHAZARDOUS MATERIALS
I.03.Require businesses handling biohazardous...
9/21/2000
10/20/2000


Pending Submission of Evidence of Certification
J.01 RISK MANAGEMENT PLAN(S)
J.01a.RMP Enforcement Provide an enforcement ...
10/6/2000
10/20/2000

5/25/1999
Timing of implementation triggered by City Fire Department review of cumulative development.
J.01b.Pre-Development Include, at a minimum...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01c.For areas where ITLs are exceeded, ident...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01d.Development Include in the RMP, health ...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01e.Identify site access controls to be impl...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01f.Identify protocols for managing soil dur...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01g.Identify protocols for managing groundwa...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01h.Include SWPPP requirements and BMPs as d...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01I.Include a requirement that construction ...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01j.Develop and describe procedures for impl...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01k.Establish procedures, as necessary, so t...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.


Applicable Phase: Cert. Of Occupancy
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
F.03 TOXIC AIR CONTAMINANTS (TACs)
F.03.Prior to issuing a certificate of occupa...




Pending Written Verification
H.01 HEAVY EQUIPMENT STORAGE
H.01.During the build-out period, store heavy...




Pending Work Plan Submittal
H.03 COMPREHENSIVE PREPAREDNESS AND RESPONSE PLAN
H.03a.Require the formulation of a comprehensi...

5/2001
7/31/2001

Submitted May 2001
J.01 RISK MANAGEMENT PLAN(S)
J.01m.Prohibit residences with unrestricted ac...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.
J.01o.Prohibit the use of shallow groundwater ...
10/6/2000
10/20/2000

5/25/1999
See Implementation Notes for J.01a.