Mission Bay
San Francisco, CA

Block Summary Report

Block: 43
Click here to view a Printable Summary Report.
If you do not have Adobe Acrobat Reader, please click on the link to download the free plug-in.

Applicable Phase: Major Phase
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.05 ARCHAEOLOGICAL MONITORING AT 19TH CENTURY CITY DUMP
D.05.Archival review suggests that deposition...
9/29/2000
10/2/2000

10/2/2000

10/2/2000
Pending City Action
E.47 TRANSPORTATION SYSTEM MANAGEMENT (TSM) PLAN
E.47b.Transit Pass Sales Sell transit passe...
9/14/2000
9/28/2000

5/4/1999:
Phase 1 Approved

5/4/1999
A conceptual TSM and strategic plan was prepared and subsequently approved on May 4, 1999.
E.47c.Employee Transportation Subsidies Pro...
9/14/2000
9/28/2000

5/4/1999:
Phase 1 Approved

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47f.Appropriate Street Lighting. Ensure t...
9/14/2000
9/28/2000

5/4/1999:
Phase 1 Approved

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47g.Transit, Pedestrian and Bicycle Route In...
9/14/2000
9/28/2000

5/4/1999:
Phase 1 Approved

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
E.47I.Flexible Work Time/Telecommuting Wher...
9/14/2000
9/28/2000

5/4/1999:
Phase 1 Approved

5/4/1999
Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
H.05 NEW FIRE STATION
H.05.At the time the San Francisco Fire Depar...
9/15/2000
9/28/2000

1/25/2001
Timing of implementation triggered by City Fire Department review of cumulative development.


Applicable Phase: Tentative Map
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.06 UNKNOWN ARCHAEOLOGICAL REMAINS
D.06.The entire Mission Bay Project Area has ...
9/29/2000
10/2/2000

10/2/2000
Pending City Action
E.15 OWENS STREET/16TH STREET
E.15a.Install a new traffic signal....
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
E.25 OWENS STREET
E.25c.Extend Owens Street northward from 16th ...
9/14/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
E.25d.Construct Owens Street between 16th Stre...
9/14/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
H.07 CORROSIVITY
H.07.Test soils for sulfate and chloride cont...
9/29/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP)
K.01.Develop and implement a comprehensive St...
9/25/2000
9/28/2000

1/25/2001:
Phase 1 Approved
A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
K.01a.Minimize dust during demolition, grading...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01b.Minimize wind and water erosion on tempo...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01c.Minimize the area and length of time dur...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01d.Prevent the release of construction poll...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01e.As needed, install filter fences around ...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01f.Follow design and construction standards...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01g.Install and maintain sediment and oil an...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01h.Clean wheels and cover loads of trucks c...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01I.Implement a hazardous material spill pre...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.02 CHANGES IN SANITARY SEWAGE QUALITY
K.02.In addition to developing and implementi...
9/29/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending City Action
K.03 SEWER IMPROVEMENT DESIGN
K.03.Design and construct sewer improvements ...
9/25/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
K.05 CENTRAL/BAY BASIN STORMWATER MANAGEMENT PROGRAM
K.05.Develop and implement a Stormwater Manag...
9/25/2000
9/28/2000

1/25/2001:
Phase 1 Approved
The Stormwater Management Plan was completed and deemed acceptable in October 2001 by the Department of Public Works. Individual requirements may apply to all sites.
K.06 STRUCTURE PLACEMENT AND DESIGN TO MINIMIZE DANGERS OF FLOODING
K.06.Structures in the Project Area should be...
9/25/2000
9/25/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
K.06c.Provide for dewatering basements...
9/25/2000
9/25/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
K.06f.Use half-basements and partially depress...
9/25/2000
9/25/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
M.04 SEWERS AND WASTEWATER TREATMENT
M.04.Construct a fence around any interim sur...
9/29/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
M.05 STORMWATER RUNOFF CONTROL AND DRAINAGE
M.05.Drain stormwater runoff (up to a 5-year ...
9/25/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection


Applicable Phase: Project Level Review
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.01 LIGHTING AND GLARE
D.01.Design parking structure lighting to min...
9/25/2000
9/28/2000


Pending Design Submission
D.07 PEDESTRIAN-LEVEL WINDS
D.07.Require a qualified wind consultant to r...
9/25/2000
9/28/2000


Pending Design Submission
D.08 SHADOWS
D.08.The Redevelopment Plan documents would r...
9/25/2000
9/28/2000


Pending Design Submission
K.02 CHANGES IN SANITARY SEWAGE QUALITY
K.02.In addition to developing and implementi...
9/29/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending City Action


Applicable Phase: Improvement Plan - Plan Check
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
E.15 OWENS STREET/16TH STREET
E.15a.Install a new traffic signal....
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Construction and Inspection
K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP)
K.01.Develop and implement a comprehensive St...
9/25/2000
9/28/2000

1/25/2001:
Phase 1 Approved
A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
K.01b.Minimize wind and water erosion on tempo...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01c.Minimize the area and length of time dur...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01d.Prevent the release of construction poll...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01e.As needed, install filter fences around ...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01f.Follow design and construction standards...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01g.Install and maintain sediment and oil an...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01h.Clean wheels and cover loads of trucks c...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP
K.01I.Implement a hazardous material spill pre...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP


Applicable Phase: Building Site Permit
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
D.06 UNKNOWN ARCHAEOLOGICAL REMAINS
D.06.The entire Mission Bay Project Area has ...
9/29/2000
10/2/2000

10/2/2000
Pending City Action
F.02 CONSTRUCTION PM
F.02.As conditions of construction contracts,...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02a.Water all active construction areas at l...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02b.Use tarpaulins or other effective covers...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02c.Pave, apply water three times daily, or ...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02d.Sweep all paved access routes, parking a...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02e.Sweep streets daily (preferably with wat...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02f.Hydroseed or apply (non-toxic) soil stab...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02g.Enclose, cover, water twice daily or app...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02h.Limit traffic speeds on unpaved roads to...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02I.Install sandbags or other erosion contro...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02j.Replant vegetation in disturbed areas as...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02k.Install wheel washers for all exiting tr...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02l.Install wind breaks, or plant trees / ve...



1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02m.Suspend excavation and grading on large ...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
F.02n.Limit the area subject to excavation, gr...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Conditioned on Subdivision Map and/or Improvement Plans
J.01 RISK MANAGEMENT PLAN(S)
J.01d.Development Include in the RMP, health ...
9/27/2000
9/28/2000

5/25/1999
Timing of implementation triggered by City Fire Department review of cumulative development.
J.01e.Identify site access controls to be impl...
9/27/2000
9/28/2000

5/25/1999
See Implementation Notes for J.01d.
K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP)
K.01a.Minimize dust during demolition, grading...
9/27/2000
9/28/2000

1/25/2001:
Phase 1 Approved
Pending Submission of Site Specific SWPPP


Applicable Phase: Cert. Of Occupancy
Mitigation Measure RBF Review Date City Review Process Approval Date Implementation
Submitted Review Completed
F.03 TOXIC AIR CONTAMINANTS (TACs)
F.03.Prior to issuing a certificate of occupa...



Phase 1 Approved
Pending Written Verification
H.03 COMPREHENSIVE PREPAREDNESS AND RESPONSE PLAN
H.03a.Require the formulation of a comprehensi...
9/25/2000
5/2001
7/31/2001

Submitted May 2001
H.03b.In addition to the Project Area-wide pla...
9/25/2000
9/28/2000


Pending Building Construction