| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.06 UNKNOWN ARCHAEOLOGICAL REMAINS |
| D.06. | The entire Mission Bay Project Area has ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| E.47 TRANSPORTATION SYSTEM MANAGEMENT (TSM) PLAN |
| E.47f. | Appropriate Street Lighting.
Ensure t...
 |
 |
 |
 |
 | A conceptual TSM and strategic plan was prepared and subsequently approved on May 4, 1999. Implementation of the specific measures within the Conceptual TSM may be applied to individual sites as determined by the TMA.
 |
| E.47g. | Transit, Pedestrian and Bicycle Route In...
 |
 |
 |
 |
 | See Implementation Notes for E.47f.
 |
| E.49 FERRY SERVICE |
| E.49. | Ferry Service
Make a good faith effor...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.01 TSM MEASURES |
| F.01. | Implement measures to decrease vehicle t...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| H.05 NEW FIRE STATION |
| H.05. | At the time the San Francisco Fire Depar...
 |
 |
 |
 |
 | Timing of implementation triggered by City Fire Department review of cumulative development.
 |
| H.06 FACILITATE EMERGENCY ACCESS ROUTES |
| H.06. | As part of the comprehensive preparednes...
 |
 |
 |
 |
 |
 |
| M.06 CONSTRUCT NEW FIRE STATION AND PROVIDE NEW ENGINE COMPANY |
| M.06a. | Construct New Fire Station
Construct or...
 |
 |
 |
 |
 | Timing of implementation triggered by City Fire Department review of cumulative development.
 |
| M.06b. | Provide New Engine Company
Provide or p...
 |
 |
 |
 |
 | Timing of implementation triggered by City Fire Department review of cumulative development.
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.05 ARCHAEOLOGICAL MONITORING AT 19TH CENTURY CITY DUMP |
| D.05. | Archival review suggests that deposition...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| E.25 OWENS STREET |
| E.25b. | Construct Owens Street between Fourth St...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| E.25c. | Extend Owens Street northward from 16th ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| E.26 NORTH COMMON AND SOUTH COMMON STREETS CONNECTION TO SEVENTH STREET |
| E.26a. | Construct an “at-grade” connection to Se...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| E.28 MUNI LINE 30-STOCKTON OR 45-UNION/STOCKTON |
| E.28. | Extend about half of the 30-Stockton or ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.01 TSM MEASURES |
| F.01. | Implement measures to decrease vehicle t...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| H.07 CORROSIVITY |
| H.07. | Test soils for sulfate and chloride cont...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP) |
| K.01a. | Minimize dust during demolition, grading...
 |
 |
 |
 |
 | A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
 |
| K.01b. | Minimize wind and water erosion on tempo...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01c. | Minimize the area and length of time dur...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01d. | Prevent the release of construction poll...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01e. | As needed, install filter fences around ...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01f. | Follow design and construction standards...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01g. | Install and maintain sediment and oil an...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01h. | Clean wheels and cover loads of trucks c...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01I. | Implement a hazardous material spill pre...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.03 SEWER IMPROVEMENT DESIGN |
| K.03. | Design and construct sewer improvements ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.04 ALTERNATIVE TECHNOLOGIES TO IMPROVE STORMWATER DISCHARGE QUALITY |
| K.04. | Implement alternative technologies or us...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06 STRUCTURE PLACEMENT AND DESIGN TO MINIMIZE DANGERS OF FLOODING |
| K.06. | Structures in the Project Area should be...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06a. | Setback from the water’s edge...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06b. | Install seawalls, dikes, and/or berms du...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06c. | Provide for dewatering basements...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06d. | Construct streets and sidewalks above ex...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06e. | Use topsoil to raise the level of public...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| K.06f. | Use half-basements and partially depress...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| M.04 SEWERS AND WASTEWATER TREATMENT |
| M.04. | Construct a fence around any interim sur...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| M.05 STORMWATER RUNOFF CONTROL AND DRAINAGE |
| M.05. | Drain stormwater runoff (up to a 5-year ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| J.01 RISK MANAGEMENT PLAN(S) |
| J.01l. | Post-Development
Except where testing d...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| K.01 STORMWATER POLLUTION PREVENTION PROGRAM (SWPPP) |
| K.01a. | Minimize dust during demolition, grading...
 |
 |
 |
 |
 | A Conceptual SWPPP was prepared and completed by California Soil & Environmental Consultants Inc. on November 1999. Implementation of the specific measures within the plan may be applied to individual sites as determined by the PUC.
 |
| K.01b. | Minimize wind and water erosion on tempo...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01c. | Minimize the area and length of time dur...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01d. | Prevent the release of construction poll...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01e. | As needed, install filter fences around ...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01f. | Follow design and construction standards...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01g. | Install and maintain sediment and oil an...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01h. | Clean wheels and cover loads of trucks c...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| K.01I. | Implement a hazardous material spill pre...
 |
 |
 |
 |
 | See Implementation Notes for K.01a.
 |
| Mitigation Measure | RBF Review Date | City Review Process | Approval Date | Implementation |
| Submitted | Review Completed |
| D.06 UNKNOWN ARCHAEOLOGICAL REMAINS |
| D.06. | The entire Mission Bay Project Area has ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02 CONSTRUCTION PM |
| F.02. | As conditions of construction contracts,...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02a. | Water all active construction areas at l...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02b. | Use tarpaulins or other effective covers...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02c. | Pave, apply water three times daily, or ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02d. | Sweep all paved access routes, parking a...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02e. | Sweep streets daily (preferably with wat...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02f. | Hydroseed or apply (non-toxic) soil stab...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02g. | Enclose, cover, water twice daily or app...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02h. | Limit traffic speeds on unpaved roads to...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02I. | Install sandbags or other erosion contro...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02j. | Replant vegetation in disturbed areas as...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02k. | Install wheel washers for all exiting tr...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02l. | Install wind breaks, or plant trees / ve...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02m. | Suspend excavation and grading on large ...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| F.02n. | Limit the area subject to excavation, gr...
 |
 |
 |
 |
 | Pending Application Submittal
 |
| J.01 RISK MANAGEMENT PLAN(S) |
| J.01. | Prior to any site development activities...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01a. | RMP Enforcement
Provide an enforcement ...
 |
 |
 |
 |
 | Timing of implementation triggered by City Fire Department review of cumulative development.
 |
| J.01b. | Pre-Development
Include, at a minimum...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01c. | For areas where ITLs are exceeded, ident...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01d. | Development
Include in the RMP, health ...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01e. | Identify site access controls to be impl...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01f. | Identify protocols for managing soil dur...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01g. | Identify protocols for managing groundwa...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01h. | Include SWPPP requirements and BMPs as d...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01I. | Include a requirement that construction ...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01j. | Develop and describe procedures for impl...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |
| J.01k. | Establish procedures, as necessary, so t...
 |
 |
 |
 |
 | See Implementation Notes for J.01a.
 |